LEAG GigaBattery Boxberg: 400 MW / 1.6 GWh where cooling towers once stood

On the site of the old Boxberg power plant LEAG is building a 400 MW / 1,600 MWh battery – four hours of storage, connected to the 380 kV transmission grid.

What does this mean for you?

Structural change becomes a storage boom. Lusatia shows how coal regions keep using their grid connections. Companies in coal regions should look at structural-change funding and contracts around construction, grid connection and operation.

Four hours instead of one: the trend is towards longer durations. That opens opportunities for cooling, fire protection, container construction and energy management software.

Four cooling towers of the decommissioned old power plant were dismantled for the battery. On around six hectares the GigaBattery Boxberg 400 is being built with 400 MW and 1,600 MWh (four hours).

  • Technology partner / turnkey contractor: HyperStrong (HyperBlock III system, LFP cells)
  • Siemens Energy supplies the 380 kV switchgear connecting to the 50Hertz transmission grid
  • construction start reported in early September 2026; commissioning expected end of 2027 to early 2028 according to LEAG
  • purpose: integrating wind and solar, primary and secondary balancing power
  • partly funded by the EU Just Transition Fund

Sources

  1. [1]LEAG – GigaBatteries in Lusatia· accessed 2026-11-28
  2. [2]ess-news – Leag starts building 1.6 GWh battery storage system (01.09.2026)· accessed 2026-11-28
  3. [3]Energy-Storage.news – Hyperstrong starts building LEAG's 1.6GWh Germany BESS· accessed 2026-11-28

Let's talk about your plans.

Site, storage, data center or new markets for your components – write to us and we will get back to you personally.